Client
???????
Location
???????
Date
12 Jan, 2023
Skill
3D Design, Revit – Preliminary and Construction issue GA’s, Advanced Steel – Detailed fabrication drawings
TIME TAKEN
Design period 5 days – Fabrication time 2 weeks – Site Installation 5 days
Prior to design progression site surveys were carried out in order to produce Preliminary Construction drawings allowing design development to progress incorporating any further revisions required as a result of client, design team and fabricator input.
Upon final approval Construction Status drawing were issued and fabrication drawings were produced and then issued to the fabricator for manufacturing, all mild steel components were then sent off to a specialist for application of the specified Polyester Powder Coat paint system prior to site installation by the fabricators steel erectors.